MINISTERIAL
Over-the-counter permit — no discretionary review
Ashby Small Infill
Ashby BART Station Area
10 units — below 15-unit threshold
10 units
× 2.5 veh/unit
× 90% evac. rate
= 0 vph
Non-FHSZ
DISCRETIONARY
Planning Commission review required — public hearing
Downtown Mid-Rise
Shattuck Ave & Center St, Downtown Berkeley
Adeline Street: ΔT 6.04 min — 1.0× the 6.00-min limit
6.04 min / 6.00 min limit
85 units
× 2.5 veh/unit
× 90% evac. rate
= 191 vph
Non-FHSZ
DISCRETIONARY
Planning Commission review required — public hearing
Hills Gateway
Claremont Ave & Tunnel Rd
Shasta Road: ΔT 27.43 min — 12.2× the 2.25-min limit
27.43 min / 2.25 min limit
80 units
× 2.5 veh/unit
× 90% evac. rate
= 180 vph
VHFHSZ
MINISTERIAL
Over-the-counter permit — no discretionary review
Hills FHSZ Small Infill
Tunnel Rd & Claremont Ave, Berkeley Hills (FHSZ Zone 3 area)
10 units — below 15-unit threshold
10 units
× 2.5 veh/unit
× 90% evac. rate
= 0 vph
VHFHSZ
MINISTERIAL WITH STANDARD CONDITIONS
Staff approval — standard conditions apply automatically; no public hearing
Claremont Hills Terrace
Ridge Road & Claremont Ave, Berkeley Hills
All paths within limit · Ridge Road: 3.00 min (50% used, 3.00 left)
3.00 min / 6.00 min limit
25 units
× 2.5 veh/unit
× 90% evac. rate
= 56 vph
Non-FHSZ
DISCRETIONARY
Planning Commission review required — public hearing
Cedar Street Infill
Cedar Street & Shattuck Ave, North Berkeley
North Street: ΔT 18.00 min — 3.0× the 6.00-min limit
18.00 min / 6.00 min limit
75 units
× 2.5 veh/unit
× 90% evac. rate
= 169 vph + 9.0 min egress (NFPA 101)
Non-FHSZ